Kuhlman Electric Corporation Crystal Springs MS

**Corrective Action Plan**, March 2011 **Corrective Action Plan**, October 2010

**Soil Vapor Extraction Pilot Test Plan, January 2012

Reports
KEC Semi Annual Assessment Rept 01.03.2012
KEC GWMW Install Report 02.22.2012
KEC Lake Chautauqua Sediment and Soil Sampling Plan 06.06.2012
Capacity Plan Outline 06.06.2012
Final KEC Semi Annual Assessment Rept 07.31.2012
Final 2nd Quarter Monitoring Report 10.03.2012
Final Upgradient Work Plan 10.03.2012
Final CEP 10.31.2012
KEC SVE Pilot Study Report
Upgradient Shallow Subsurface Investigation Report 041013

Additional
Show details for Lake Chautauqua Revised Biological Investigation Work PlanLake Chautauqua Revised Biological Investigation Work Plan
Hide details for Brent Street Project Remediation ReportBrent Street Project Remediation Report
Brent Street Project Remediation Report
ECCS Data for 4-15 Report
1-07 TM
2-07 TM
2-19 and 2-22-07 TM
3-07 TM
3-07 #2 TM
4-07 TM
5-07 TM
SGS Data for 4-15 Report
1-30-07
2-2-07
2-12-07
2-15-07
2-19-07
2-26-07
3-5-07
3-6-07
3-8-07
3-9-07
3-16-07
3-26-07
3-27-07
4-2-07
4-5-07
4-16-07
4-19-07
4-25-07
4-30-07
5-3-07
Show details for Groundwater Interim Report IIIGroundwater Interim Report III
Show details for Groundwater Interim Report IVGroundwater Interim Report IV
Show details for Groundwater Interim Report VGroundwater Interim Report V
Show details for Puckett Street Site Assessment ReportPuckett Street Site Assessment Report
Show details for Technical MemorandumsTechnical Memorandums
Box 1
Show details for Folders 1 - 4Folders 1 - 4
Box 2
Show details for Folders 1 - 9Folders 1 - 9
Box 3
Hide details for Folders 1 - 8Folders 1 - 8
Folders 1 - 8
Folder 1 - PCB Litigation
PHASE 2 SUMMERY REPORT FEB 2001.PDF
PRIVATE RESIDENCES NOV 2000.PDF
SUMMARY REPORT JULY 2001.PDF
Folder 2 - PCB Litigation
SAMPLING REPORT 18 DEC 2001.PDF
Folder 3 - MSD 008188724
ANALYTICAL RESULTS FOR CONCRETE AND ASPHALT SAMPLES JAN 2002.PDF
DRAINAGE CHANNEL MASTER PLAN FEB 2001.PDF
MSD 008188724.PDF
REMEDIATION WORK PLAN FOR THE NORTH DRAINAGE CHANNEL.PDF
SUPPLEMENTAL REPORT PCB LITIGATION MAY 2003.PDF
VICINITY MAP.PDF
Folder 4 - AKT Gravel Pit
SITE INVESTIGATION DATA JULY 2001-1.PDF
SITE INVESTIGATION DATA JULY 2001-2.PDF
Folder 5 - AKT Gravel Pit Apr 2001
SOIL REMOVAL PLAN.PDF
Folder 6 - AKT Gravel Pit Dec 2000
REVISED SITE ASSESSMENT WORK PLAN SUBMITTAL.PDF
Folder 7 - AKT Gravel Pit July 2001
REVISED SOIL REMOVAL PLAN.PDF
Folder 8 - AKT Gravel Pit Nov 2001
SITE ASSESSMENT WORK PLAN SUBMITTAL.PDF
Box 4
Show details for Folders 1 - 8Folders 1 - 8
Box 5
Show details for Folders 1 - 7Folders 1 - 7
Box 6
Show details for Folders 1 - 36Folders 1 - 36
Box 7
Show details for Folders 1 - 22Folders 1 - 22
Box 8
Show details for Folders 1 - 13Folders 1 - 13
Box 9
Hide details for Folders 1 - 6Folders 1 - 6
Folders 1 - 6
Folder 1 - Plant Site Remediation Report June 2004 Appendix 1 Volume 6
Folder 2_1 - Plant Site Remediation Report June 2004 Appendix 4 Volume 1
Folder 2_2 - Plant Site Remediation Report June 2004 Appendix 4 Volume 1
Folder 2_3 - Plant Site Remediation Report June 2004 Appendix 4 Volume 1
Folder 3 - Plant Site Remediation Report June 2004 Appendix 4 Volume 7
Folder 4 - Plant Site Remediation Report June 2004 Appendix 2 and 3
Folder 5 - Plant Site Remediation Report June 2004 Appendix 4 Volume 6
Folder 6 - Plant Site Remediation Report June 2004 Appendix 4 Volume 2
Box 10
Show details for Folders 1 - 7Folders 1 - 7
Box 11
Show details for Folders 1 - 7Folders 1 - 7
Box 12
Show details for Folders 1 - 4Folders 1 - 4
Box 13
Show details for Folder 1 - Various ReportsFolder 1 - Various Reports

Community Engagement Documents

Crystal Springs Community Engagement Plan

COMMUNITY ENGAGMENT PROGRESS REPORT JANUARY THROUGH OCTOBER 2012

COMMUNITY ENGAGMENT PROGRESS REPORT OCTOBER 2012 THROUGH JANUARY 2013

Community Engagement Report Q1_2013

Newsletter 1
Newsletter 2