What are the estimated timeframes for obtaining the different permit types?

Estimated Timeframes for Specific Permits

    1. Air Permits
    1. PSD Construction Permit - 150 to 180 days
    2. State Construction Permit - 150 to 180 days
    3. State Operating Permit - 150 to 180 days
    4. Title V Operating Permit - 150 to 180 days
    2. General Permit Coverages
    1. 15 to 90 days
    3. Hazardous Waste RCRA Permits
    1. TSD Permit - 180 to 270 days
    4. Solid Waste Permit
    5. Water Permits
    1. NPDES Permit - 120 to 180 days
    2. State Operating No Discharge Permit - 45 to 90 days
    3. Storm Water Coverage - 15 to 90 days

What are some of the other permit applications processed by MDEQ/OPC?